Phase I - Site Preparation:
Close Walker Road, Install Fish Screens, Remove Fish and Vegetation From Project AreaPhase II - Demolition and Site Preparation:
Remove Existing Wood Culvert, Excavate Stream Bottom, Install Rock Slope Protection, Install Prefabricated Concrete Bridge FootingsPhase III - Bridge Installation: